Renewable Energy Power Purchase Agreements: Key Terms & Risks

Corporate India’s transition to renewable energy has accelerated dramatically, with Power Purchase Agreements (PPAs) emerging as the preferred mechanism for C&I consumers seeking sustainable and cost-effective electricity. However, behind the attractive tariff headlines lies a complex web of technical, commercial, regulatory, and legal considerations that demand careful scrutiny. At Lamberton, we’ve observed that corporations often prioritize headline tariffs over contractual fundamentals; a strategy that can prove costly over 15-25 year PPA tenures.

Understanding Corporate Renewable PPAs in India

Renewable energy PPAs allow corporate consumers to procure solar or wind power directly from generators, either through captive arrangements, open access mechanisms, or group captive structures. While the promise of fixed tariffs and green credentials is compelling, the devil resides firmly in the details. The Indian renewable PPA landscape presents unique challenges stemming from regulatory fragmentation across states, evolving policy frameworks, and commercial structures that often favor developers.

Technical Risk Analysis: Beyond Nameplate Capacity

Plant Performance and Degradation

Solar modules degrade at 0.6-0.8% annually, while inverter efficiency declines over time. PPAs must specify guaranteed Capacity Utilization Factors (CUF) or Plant Load Factors (PLF); typically 19-22% for solar and 25-35% for wind. However, these guarantees mean little without robust performance testing protocols, clearly defined meteorological adjustment mechanisms, and stringent liquidated damages for underperformance. We’ve encountered agreements where CUF guarantees exclude “force majeure days,” which developers liberally interpret to include routine cloud cover or low wind periods, effectively rendering guarantees meaningless.

The measurement methodology matters critically. Is performance measured at the generation meter or delivery point? Who bears transmission and distribution losses? What weather normalization standards apply? A 20% CUF guarantee measured at source becomes 18% at the consumption point after 10% T&D losses; significantly impacting your effective tariff.

Grid Availability and Scheduling Risks

India’s grid infrastructure constraints create significant technical risks. When the grid curtails renewable injection due to congestion or grid security, who compensates whom? Many PPAs place this risk entirely on consumers through “deemed generation” clauses, requiring payment for power that could have been generated but wasn’t injected due to grid unavailability. Conversely, examine provisions for DISCOM-imposed curtailment and your ability to schedule power flexibly during high-demand periods.

State Load Dispatch Centers impose deviation settlement mechanisms and scheduling charges. Poor forecasting accuracy; common with renewable sources which triggers penalties. Determine whether the PPA obligates the developer to maintain minimum forecasting accuracy (typically 70-80% for day-ahead and 90%+ for intraday) and who bears deviation charges when forecasts fail.

Technical Force Majeure and Downtime

Equipment failures, component unavailability, and maintenance downtime are inevitable. Well-structured PPAs specify maximum allowable downtime (typically 2-5% annually) and compensation mechanisms beyond these thresholds. Critically, distinguish between scheduled maintenance (which should not reduce offtake obligations) and unscheduled outages (which might trigger liquidated damages). The force majeure definition should be narrow and specific, excluding routine technical failures that competent developers should anticipate and manage.

Commercial Risk Architecture

Termination Penalties: The Financial Straitjacket

Termination clauses deserve exceptional attention. Many PPAs impose penalties calculated as the Net Present Value of future revenue streams at 10-12% discount rates, effectively requiring payment of 60-90% of remaining contract value. Some agreements structure penalties as debt repayment obligations, transferring the developer’s financing burden to consumers upon early exit. Typically this results in payments of upto 2 years of equivalent generation.

Critical questions include: Are termination rights mutual or unilateral? Can consumers terminate for sustained underperformance, developer bankruptcy, or material breach? What constitutes adequate cure periods? We recommend negotiating stepped penalty structures that decline over time and explicit materiality thresholds before termination penalties trigger. Additionally, ensure termination rights exist for regulatory changes that fundamentally alter project economics, such as withdrawal of open access permissions or prohibitive wheeling charge escalations or any other regulatory charge levied.

Change in Law: Regulatory Risk Allocation

India’s renewable sector has experienced dramatic regulatory shifts; from accelerated depreciation withdrawals to GST implementation and frequent wheeling charge revisions. Change-in-law provisions must comprehensively address both adverse and beneficial changes. Many developer-drafted PPAs allow upward tariff adjustments for any cost-increasing regulatory change while prohibiting downward adjustments when regulations favor generators.

Robust provisions should define “change in law” precisely, specify adjustment mechanisms with independent verification, establish dispute escalation for contested changes, and include symmetrical adjustment rights. For instance, if renewable purchase obligation compliance changes benefit developers through increased REC prices, consumers should share those benefits through tariff reductions. Similarly, examine how GST fluctuations, carbon pricing mechanisms, or transmission charge modifications flow through the tariff structure.

Minimum Guaranteed Consumption and Payment Security

Minimum offtake commitments typically range from 90-100% of contracted capacity, with mostly annual true-up mechanisms. This fundamentally transforms PPAs from pay-for-use contracts into capacity reservation agreements. For businesses with variable demand, manufacturing seasonality, or expansion uncertainties, such guarantees create substantial stranded cost risks.

Sophisticated analysis requires modeling your consumption patterns across seasonal variations, production cycles, and growth projections. What flexibility exists for third-party sale of surplus power? Can unused capacity be banked indefinitely or does it expire monthly/annually? Are banking charges applied, and at what rates? Some states limit banking to 30-day periods with no carry-forward, making surplus power worthless. 

Payment security mechanisms compound commercial risks. Letters of credit, bank guarantees, or advance deposits securing 2-3 months of payments are standard. However, examine whether they’re returned upon contract completion or only after final reconciliation; which can extend months beyond PPA expiry.

Minimum Savings Guarantee: The Devil in the Baseline

Savings guarantees appear consumer-protective but contain critical nuances. The baseline tariff against which savings are measured determines real value. Is it your current applicable DISCOM tariff including demand charges and fuel surcharges? Average power purchase cost? Projected future tariffs with assumed escalations?

Additionally, examine whether savings calculations occur pre- or post-ancillary charges. A PPA with  INR 1/kWh as the Minimum Savings Guarantee in a market like Maharashtra may cause issues in continuity of PPA in case there is regulatory volatility in Open access charges even if they are levied for a short term. Eg: Levy of INR 1.28/kWh  of Additional surcharge (ASC) in 2019 in Maharashtra . Developers typically need to declare a floor price on the tariff in the event Minimum Savings Guarantee is being offered to ensure that they are not contractually forced to operate the plant at a loss.

Escalation Structures and Lifecycle Costs

Fixed tariffs rarely remain fixed. Some PPAs include annual escalations of 2-3%, applied either to the entire tariff or only the variable component. Over 25 years, a ₹2.50/kWh tariff with 3% annual escalation reaches ₹5.23/kWh by year 25. Levelized cost analysis across the entire contract period provides true economic comparison. Another risk is due to the escalation , there could be an event in the future where the DISCOM cost may reduce due to the overinjection of renewables in the state.

Some developers offer lower initial tariffs with steeper escalations or back-ended payment structures. While improving initial economics, such arrangements create future cost burdens and refinancing risks if business circumstances change. Evaluate the weighted average tariff across the PPA term, discounted to present value, for accurate cost comparison.

The Lowest Tariff Trap: Total Cost of Ownership

The most dangerous tendency in corporate renewable procurement is fixation on headline tariffs. A PPA priced at ₹3.00/kWh with onerous terms routinely proves more expensive than ₹3.50/kWh with balanced risk allocation. Consider total cost of ownership:

Ancillary Charges: Wheeling (₹0.30-80/kWh), transmission (₹0.10-0.30/kWh), and scheduling charges (₹0.05-0.15/kWh) vary dramatically by state. 

Performance Risk: A ₹3.50/kWh PPA with weak CUF guarantees delivering only 85% of projected power costs effectively ₹4.11/kWh when minimum offtake obligations apply. Meanwhile, a ₹3.70/kWh agreement with strict performance guarantees and liquidated damages ensures predictable costs.

Operational Flexibility: Rigid scheduling requirements, limited banking windows, and restrictive consumption patterns add hidden costs through forced grid purchases during PPA shortfalls or wasted banked energy. Premium tariffs with superior operational flexibility often deliver lower total costs.

Creditworthiness and Longevity: Developer financial stability impacts long-term service quality, maintenance standards, and asset replacement during the 20-25 year PPA term. Undercapitalized developers offering aggressive pricing may compromise on component quality, monitoring systems, or preventive maintenance; increasing downtime and reducing effective generation. Also mostly undercapitalized developers typically flip the assets to investors after commissioning, so the person you are talking to now would be a stranger after the plant is live.

Navigating Regulatory Complexity

Indian renewable PPAs must navigate state-specific open access regulations, requiring meticulous attention to approval processes, DISCOM concurrence timelines, and compliance frameworks. Consumers should verify that PPAs explicitly address delays in regulatory approvals, allocating responsibility and providing tariff adjustments or termination rights if approvals don’t materialize within specified periods.

RPO compliance mechanisms vary by state. Does the PPA guarantee RPO credit delivery, and what recourse exists if credits aren’t issued? State electricity regulatory commissions periodically revise open access charges, Robust PPAs offer flexibility for mutual discussions or provide termination rights if charges exceed discom landed power cost.

In the event of Change in Law, how are offtakers protected? Do they have an option to exit or limit their liabilities/ offtake. What clauses would fall in a Change in Law scenario are also to be critically examined. Some developers use clever legal language to pass on the risks to the developer completely under a Change in Law.

Legal Structuring and Dispute Resolution

Robust dispute resolution mechanisms specifying arbitration forums, governing law, and escalation procedures; prevent costly litigation. Given the cross-border nature of many renewable investments, examine whether international arbitration is appropriate. Some developers will require the offtaker comply with US and UK Laws which are quite prohibitive and are expensive for litigation.  The jurisdiction should be clearly defined: is it the state where the project is located, where the consumer operates, or mutual jurisdiction?

Indemnification provisions allocate liability for third-party claims, environmental damages, and regulatory penalties. Ensure developers indemnify consumers for project-side issues including land acquisition disputes, environmental violations, or grid code non-compliance, while consumers indemnify for consumption-side matters.

Strategic PPA Evaluation Framework

Successful renewable PPAs require comprehensive due diligence across multiple dimensions. At Lamberton, we recommend:

Technical Due Diligence: Independent engineer assessment of project design, component quality, O&M capabilities, and realistic performance projections. Verify developer track record, existing asset performance, and technical team competence.

Commercial Modeling: Detailed financial modeling incorporating all cost elements, consumption projections, banking utilization, and sensitivity analysis across regulatory scenarios. Compare levelized cost of energy across competing proposals.

Legal Review: Comprehensive contract negotiation focusing on balanced risk allocation, clear dispute mechanisms, and protection against developer default or underperformance.

Regulatory Analysis: State-specific compliance verification, approval pathway mapping, and scenario planning for regulatory changes.

The lowest tariff often conceals the highest risk. Successful renewable procurement balances competitive pricing with contractual clarity, operational flexibility, and equitable risk allocation. In India’s complex regulatory environment, sophisticated PPA negotiation—not merely tariff comparison; determines whether renewable investments deliver sustained value or become expensive obligations.